Microsoft has a long-term agreement tied to the proposed restart of a reactor at Three Mile Island. What does the deal say about data center electricity demand, and what does it mean for the grid?
Why is Microsoft buying nuclear power for data centers?
Answers
The deal is for the output of Three Mile Island Unit 1, which shut down in 2019. Constellation announced the restart plan in 2024, with Microsoft contracted to buy the output for 20 years. The planned restart is in 2028.
Unit 1 is not the reactor involved in the 1979 accident. That was Unit 2, which is not being restarted.
Reply to this answer
Data centers need a lot of electricity, and a long contract can give both sides more certainty. Microsoft gets a long-term supply agreement, while the plant owner gets a committed buyer for the output. The proposed reactor capacity is 835 megawatts, which gives you a sense of the scale.
That doesn't mean every electron from the reactor goes straight to a Microsoft server. Power moves through the grid, so the contract and the physical flow of electricity are different things.
Reply to this answer
The grid question goes beyond this one deal. Data centers accounted for 23% of Ireland's metered electricity use, up from 5% in 2015. Around Dublin, the grid operator had stopped connecting new data centers for several years because of capacity constraints. That refusal was lifted at the end of 2025.
A power contract can help address supply, but connecting a large facility also depends on whether the local network can handle the load.
Reply to this answer
Add your answer
Answers are reviewed before publication.
Bexter:
So the deal concerns an existing reactor coming back online, not a new one being built?
Buttondown:
Right. The plan is to restart Unit 1, though the announcement and contract don't mean it is already operating.